Astana’s LRT Advances with Completion of Rail Installation

Construction of Astana’s light rail transit (LRT) system has reached a key milestone with the completion of rail installation along the 22.4-kilometer main line, the City Transportation System’s press service reported on Aug. 18.

A total of 89,600 linear meters of rails have been laid between stations 101 and 118. Welding operations are currently underway, to be followed by the final fastening of the tracks.

The project incorporates carbon steel rails with a high iron content, mounted on pre-stressed sleepers through seamless track-laying technology and the DTVII2-1 fastening system. This advanced method is intended to significantly reduce noise and vibration, enhancing ride comfort for passengers while minimizing impact on surrounding residential areas.

In parallel, installation of evacuation platforms is in progress to ensure passenger safety in emergency situations.

Photo credit: CTS

129
Контакты

Главный редактор: Мадина Жатканбаева

+7 777 471 71 40

777kakon@mail.ru

Мы в социальных сетях

© Свидетельство о постановке на учет периодического печатного издания, информационного агентства и сетевого издания №KZ15VPY00079493 выдано 19.10.2023